Essex North Shore Agricultural and Technical School District

February 2013

Site Work

  • 40,000+ Cubic yards of loam moved
  • 70,000+ Cubic yards of common fill moved
  • 15,000+ Tons of crushed stone installed
  • 20,000+ Tons of structural fill imported
Concrete Work
  • 8,010 Cubic yards of structural concrete placed
  • 385 Tons of reinforcing steel installed
  • Structural Steel Work
  • 1,800+ Tons of steel erected
  • 300,000+ Square feet of steel decking installed
Plumbing
  • 50,000+ Gallons of rainwater reuse collection tanks installed
  • New water service installed                                                         
Electrical
  • Over three MILES of underground conduit installed
  • Temporary service installed and active

 

 

 

 

November 2012
11-27-2012 ENSAT Look Ahead

         

October 2012
10-16-2012 ENSAT Look Ahead

Site work:

  • Cuts and fills and Lower Middleton Field to be completed
  • Under drainage at Lower Middleton Field
  • Seed Lower Middleton Field
  • Backfill north wall
  • Complete sanitary, drainage and water services at access road

Concrete work:

  • Continue building D green house footings and walls
  • Start Building F footings and walls
  • Start Building E footings

Steel work:

  • Continue steel erection and deck and detail at sequence 7, 8, 9
  • Start erection of sequence 13 and sequence 16

Farmstead:

  • Finish drain and sewer
  • Start H2O
  • Start electrical conduit
  • Import structural fill
  • Excavate Small Engines
  • Prep/Pour Small Engines

  

September 2012

  • Versa-Lok wall work and backfill continue
  • Cuts and fills at upper and lower Middleton fields
  • Backfill of high walls
  • Excavation and prep of buildings continue
  • Perimeter footings and gradebeams for buildings A, B, C, and D complete by end of September
  • Underground plumbing work to begin
  • Large crane now on site for steel erection

 

 

 

 

 

 

 

 

August 2012

  • Versa-Lok wall work continues
  • Drainage, sanitary and water utilities work continues
  • Light pole bases are installed with Versa-Lok
  • Excavation continues for shallow and column footings
  • High wall footings complete at Building A, B, and D
  • Prep work for water proofing begins

July 2012

  • Versa-Lok retaining wall work continues east to west
  • Subgrade prep work is completed for footings
  • Concrete is poured for shallow and high wall footings for Buildings A, B, and C
  • Site work and abatement containment starts on farmstead week of 7/23